City of Norton – Upper Norton Dam and Spillway Improvements

City of Norton – Upper Norton Dam and Spillway Improvements

City of Norton – Upper Norton Dam and Spillway Improvements

City of Norton – Upper Norton Dam and Spillway Improvements

The City of Norton owns and operates two impoundments for water supply purposes, one situated above the other on Benges Branch, to the south and above the downtown area. The upper dam was completed in 1959 and modified in 1997. The reservoir is a 73 foot deep earthen structure with a maximum capacity of 202 acre-feet. Regulations require that the reservoir be capable of safely passing the Probable Maximum Flood (PMF). The City of Norton partnered with T&L to plan, design, permit and construct improvements to the Upper Norton Dam and spillway.

A summary of T&L’s services includes:

  • Preparation of a Preliminary Engineering Report (PER) to evaluate alternative solutions for improvements to the existing impoundment;
  • Evaluation of the existing spillway capacity;

The PER recommended that an auxiliary spillway be constructed to increase capacity for passage of the PMF. To retain the same pool elevation and provide an adequate channel for the spillway, a labyrinth spillway (shaped like a “zigzag”) was utilized due to space considerations.

Major design and construction elements included:

  • A 50-foot wide reinforced concrete auxiliary spillway chute with energy dissipation at the outlet;
  • Structural concrete chute walls to contain spillway flows; and
  • A labyrinth weir at the inlet of the spillway.

This project was completed in 2013, with a construction cost of approximately $2,232,000.

Photos

Client:
City of Norton

 

Service Type:
Civil Engineering 

 

Project Value:
$2.232 Million

 

Completion Date:
2013

 

City of Bedford Stoney Creek Dam

City of Bedford Stoney Creek Dam

Town of Bedford Stoney Creek Dam

T&L was retained by the Town of Bedford (formerly City of Bedford) to investigate and make recommendations regarding spillway and other repairs to the Stoney Creek Dam. Following the development of a Flood Inundation Study, Preliminary Engineering Report, and Geotechnical Analysis, it was determined that certain improvements to the Dam were required.

These improvements included:

  • Repairs on the existing Dam spillway; and
  • Construction of an auxiliary spillway to increase capacity

These improvements were addressed by the design and construction of several improvements which involved:

  • Structural repairs to the concrete chute spillway;
  • Structural concrete chute walls to contain spillway flows; and
  • A roller compacted concrete auxiliary spillway to bring the total spillway capacity up to the probable maximum flood flow requirements.

Photos

Client:
Town of Bedford

Service Type:
Civil Engineering 

Project Value:
$5.34 Million

Completion Date:
2012

 

Logan County PSD – Water Project Experience

Logan County PSD – Water Project Experience

Logan County PSD – Water Project Experience

Location: Logan County, West Virginia

Project: Mud Fork/Rum Creek Water Distribution System with booster station and a 100,000-storage tank.
Est. Cost: $1,000,000
Status: Completed 1983

Project: Phase I of Huff Creek Christian water system comprising a water distribution system, a 100,000-gallon water storage tank and a 350 gpm water treatment facility with an upgraded capacity of 700 gpm. Project also includes raw water intake and presedimentation basin
Est. Cost: $1,070,000
Status: Completed 1985

Project: Phase II of Huff Creek Christian Water System comprising a water distribution system and a 150,000 gallon water storage tank.
Est. Cost: $694,000
Status: Completed 1986

Project: Preliminary and final design, bidding and negotiating and construction administration for the Sharples emergency water system and replacement water system comprising well pump replacements, a water distribution system, a 100,000 gallon water storage tank and a 100 gpm pressure filter water treatment plant.
Est. Cost: $706,250
Status: Completed 1986

Project: Phase III of Huff Creek Christian Water System comprising a water distribution system and a 200,000 gallon water storage tank.
Est. Cost: $840,300
Status: Completed 1990

Project: Phase IV of Huff Creek Christian Water System comprising of a 200,000 gallon water storage tank, booster pump station and water distribution system.
Est. Cost: $1,000,000
Status: Completed 1993

Project: Dingess Run Waterline Extension Project comprising of water distribution lines, one 65,000-gallon water storage tank, one 200,000-gallon water storage tank and two booster pump stations.
Est. Cost: $1,250,000
Status: Completed 1996

Project: Whitman Creek Waterline Extension Project comprising of water distribution lines, one 140,000-gallon water storage tank, one 183,000-gallon water storage tank, and one booster pump station.
Est. Cost: $2,000,000
Status: Completed 1998

Project: Regional Jail Waterline Extension Project comprising of water distribution lines, one 250,000 gallon water storage tank and one high pressure booster pump station.
Est. Cost: $2,000,000
Status: Completed 1998

Project: Elk Creek – Verner Waterline Extension Project comprised of water distribution lines, one 88,000-gallon water storage tank and one 58,000-gallon water storage tank and one booster pump station.
Est. Cost: $1,270,000
Status: Completed 1999

Project: Garrett’s Fork Water Distribution System Extension Project comprised of 12” and smaller water distribution lines and two pressure reducing stations.
Est. Cost: $2,050,000
Status: Completed 2002

Project: Crawley Creek Water Distribution System Extension Project comprised of 10” and smaller water distribution lines, one 300,000-gallon water storage tank, one 200,000-gallon water storage tank and one booster pump station.
Est. Cost: $3,900,000
Status: Completed 2000

Project: Pine Creek Water Distribution System Extension Project comprised of 12” and smaller water distribution lines, one 300,000-gallon water storage tank and one high head booster pump station.
Est. Cost: $1,590,000
Status: Completed 2000

Project: Caney Branch/Rocky Branch Water Distribution System Extension Project comprised of eight inches and smaller water distribution lines, one 115,000-gallon water storage tank and one booster pump station.
Est. Cost: $2,145,000
Status: Completed 2006

Project: Northfork Water Distribution System Extension Project comprised of 8” and smaller water distribution lines, one 154,000-gallon water storage tank and one booster pump station.
Est. Cost: $2,295,000
Status: Completed 2009

Project: Huff Creek Water Distribution System Extension Project, Phase V comprised of 10” and smaller water distribution lines, one 142,000 gallon water storage tank, one 158,000 gallon water storage tank and two booster pump stations. This system serves into Wyoming County.
Est. Cost: $3,600,000
Status: Completed 2004

Photos

Client:
Logan County PSD 

Service Type:
Civil Engineering 

Project Value:
N/A

Completion Date:
N/A

Project Area:
N/A

Wilderness PSD – Water Project Experience

Wilderness PSD – Water Project Experience

Wilderness PSD – Water Project Experience

Location: Nicholas County, West Virginia

Feasibility, design construction administration and inspection of water systems consisting of the following projects:

Project: Phase I
100,000 gallon water storage facility
200,000 gallon water storage facility
350 gpm surface water treatment facility & raw water intake from Meadow River
20 mile distribution lines
Est. Cost: $2,000,000
Status: Begin 1977 Operational 1981

Project: Phase II Water Distribution System Expansion
Est. Cost: $150,000
Status: Begin 1982 Operational 1983

Project: Phase III Water Distribution Expansion with Two Pressure Booster Stations, and rate of flow controllers.
Est. Cost: $1,100,000
Status: Begin 1984 Operational 1986

Project: Phase IV Water Distribution Expansion with Booster Station, Two Storage tanks and rate of flow controller.
Est. Cost: $1,400,000
Status: Complete 1992

Project: Phase V Water Distribution Expansion with Two Pressure Reducing Stations.
Est. Cost: $1,300,000
Status: Design Complete in April 1997 – Operational 1998

Project: Phase VI Water Distribution Expansion with Two Elevated Storage Tanks, Booster Station and Two Pressure Reducing Stations.
Est. Cost: $3,700,000
Status: Operational 2003

Photos

Client:
Wilderness PSD

Service Type:
Civil Engineering 

Project Value:
N/A

Completion Date:
N/A

Project Area:
N/A

McDowell County Public Service Authority – Water Project Experience

McDowell County Public Service Authority – Water Project Experience

McDowell County Public Service Authority – Water Project Experience

Location: McDowell County, West Virginia

Project: Town of Iaeger
80-gpm water treatment plant
100,000 gallon water storage tank
8”, 6” and smaller water distribution lines
Est. Cost: $4,600,000
Status: Phase I Substantially Complete

Project: City of War Water Project
two 150,000-gallon water storage tanks
10”, 8”, 6” and smaller water distribution lines
Est. Cost: $4,800,000
Status: Preliminary Engineering Report Complete

Project: Caretta/Coalwood Water Systems Replacement
72-gpm water treatment plant
114-gpm water treatment plant
two 100,000-gallon water storage tanks
distribution systems in each community
Est. Cost: $2,965,000
Status: Complete

Project: Hemphill, Capels, Havaco, Wilcoe Water Systems
8”, 6” and smaller water distribution lines
One 30,000-gallon water storage tank
Est. Cost: $1,950,000
Status: Complete

Project: Bartley/English Water System
8”, 6” and smaller water distribution lines
200 GPM water treatment plant
One 183,000 gallon water storage tank
Est. Cost: $1,900,000
Status: Complete

Photos

Client:
McDowell County Public Service Authority

Service Type:
Civil Engineering 

Project Value:
N/A

Completion Date:
N/A

Project Area:
N/A