McDowell County Public Service Authority – Water Project Experience
Location: McDowell County, West Virginia
Project: Town of Iaeger
80-gpm water treatment plant
100,000 gallon water storage tank
8”, 6” and smaller water distribution lines
Est. Cost: $4,600,000
Status: Phase I Substantially Complete
Project: City of War Water Project
two 150,000-gallon water storage tanks
10”, 8”, 6” and smaller water distribution lines
Est. Cost: $4,800,000
Status: Preliminary Engineering Report Complete
Project: Caretta/Coalwood Water Systems Replacement
72-gpm water treatment plant
114-gpm water treatment plant
two 100,000-gallon water storage tanks
distribution systems in each community
Est. Cost: $2,965,000
Status: Complete
Project: Hemphill, Capels, Havaco, Wilcoe Water Systems
8”, 6” and smaller water distribution lines
One 30,000-gallon water storage tank
Est. Cost: $1,950,000
Status: Complete
Project: Bartley/English Water System
8”, 6” and smaller water distribution lines
200 GPM water treatment plant
One 183,000 gallon water storage tank
Est. Cost: $1,900,000
Status: Complete
Client:
McDowell County Public Service Authority
Service Type:
Civil Engineering
Project Value:
N/A
Completion Date:
N/A
Project Area:
N/A